Phu Quoc Power Link

In Vietnam, the Coastal Victory contributed to the construction and implementation of a submarine power cable link of 56 kilometers.

The objective of the construction was to establish a connection between the Phu Quoc Island and the national grid in Vietnam. The Anchor Handling Tug was deployed to handle the anchors, of ten tonnes each, and to relocate the cable laying pontoon in ultra shallow water. The depth of the water was between three and ten meters.


This project had a duration of four months, was completed in 2014, and consisted of: anchor handling and relocation of cable lay pontoons.

Related vessels

Coastal Victory
Warning: Fraud Alert

It came to our attention that fraudsters are contacting individuals, posing as employees of Acta Marine, offering various attractive vacancies in the marine industry. They extort personal data and attempt to scam by asking for money before applying to the vacancy. Acta Marine and their third-party manning agents will never ask you to transfer money to apply to one of our vacancies. Please be vigilant and do not share your personal information or transfer any money. If you receive such a message, contact us immediately via info@actamarine.com.